13.12.2019

Improved performance

The aggregates production of OAO “Uralasbest” was optimized in 2019 by means of a new crushing and screening plant.
  
The enterprise was faced with the tasks of replacing an inefficient obsolete crushing plant based on an asbestos production factory. It was necessary to reduce the rock mass transportation cost by means of preliminary crushing and separation of required aggregates fractions for the own needs of the open pit.

We have elaborated the project using a complex approach. The solution included engineering, supply of all required equipment and steel structures, installation supervision and commissioning by our service engineers. The result has already surpassed the expectations. The peak achieved capacity is 600 tons per hour, which is higher than the guaranteed value.

For more details, visit section Business/Projects/ OAO “Uralasbest” crushing and screening plant